Construction crews will be working on Panorama Drive starting Monday, May 6 through Thursday, May 23. The road will be closed southbound from Saguaro Blvd to Saguaro Blvd with only northbound traffic traveling one way. Work hours will be between 6am & 5pm Monday through Friday.
- Milling- Southbound- Monday May 6th at 7:00AM. Milling takes the asphalt layer and the subgrade layer off the roadway for a total of 3-4” of material.
- Grading- Southbound will begin Wednesday May 8th at 7:00 AM. Grading will ensure there is a strong foundation and account for adequate waterflow on the new road surface.
- Paving is tentatively scheduled for Wednesday, May 22nd & May 23rd at 7:00 AM. Paving will require 5 to 6 hours to cure once it has been rolled. This date is flexible due to inclement weather and other unforeseen issues that may arise during construction.
Emergency (Police & Fire), Recycling & Trash services will not be impacted by construction. They will have access twenty-four hours per day, seven days per week. In the event of an emergency, contact 911.